Production lead times

Production lead times

An indicative guide to help start the scheduling conversation. Confirm your project’s requirements and timing with our team before making arrangements.

Published production guide

Indicative manufacturing times

Guide updated: 9 September 2026.

Use these indicative times to begin planning your order. Current capacity, drawing approvals and the scope of your package will affect the confirmed production schedule.

Call (03) 9308 0166 for the latest information.

Indicative production lead times · 9 September 2026
ProductPublished lead time
Roof Trusses2 weeks
Prefab Walls3–4 weeks
Floor Trusses1–2 weeks
Timber3–4 days

Production timing and transportation arrangements should be confirmed separately for your order.

Useful information

Your questions,
answered.

Need something more specific?
Talk to our team

When does my lead time begin?

Ask the team which order, drawing and approval requirements need to be completed before production can be scheduled.

What if I have a required site date?

Include your preferred date with the enquiry. The team will review it against the project scope and available production capacity.

Can a plan revision affect timing?

Yes, revisions may require review and changes to detailing or manufacture. Notify the team promptly and confirm any impact on the programme.