Production lead times
Production lead times
An indicative guide to help start the scheduling conversation. Confirm your project’s requirements and timing with our team before making arrangements.
Published production guide
Indicative manufacturing times
Guide updated: 9 September 2026.
Use these indicative times to begin planning your order. Current capacity, drawing approvals and the scope of your package will affect the confirmed production schedule.
Call (03) 9308 0166 for the latest information.
| Product | Published lead time |
|---|---|
| Roof Trusses | 2 weeks |
| Prefab Walls | 3–4 weeks |
| Floor Trusses | 1–2 weeks |
| Timber | 3–4 days |
Production timing and transportation arrangements should be confirmed separately for your order.
When does my lead time begin?
Ask the team which order, drawing and approval requirements need to be completed before production can be scheduled.
What if I have a required site date?
Include your preferred date with the enquiry. The team will review it against the project scope and available production capacity.
Can a plan revision affect timing?
Yes, revisions may require review and changes to detailing or manufacture. Notify the team promptly and confirm any impact on the programme.
Project enquiries
Send us your plans.
Share your drawings, site address and required products. Talk to our Somerton team about your next order.